Watermain Replacement Project Construction Schedule

June 09, 2021

Mobilization of equipment and materials:  Begin June 14

Atlantic Avenue:  June 21 to July 14

Altantic Avenue (downtown) roads and sidewalks will begin July 6, with the intent to complete by end of July.  Existing sidewalks will remain in place as long as possible.

Manitoba Avenue:  July 14 to July 26

Saskatchewan Avenue:  July 26 to August 23

Alberta Avenue:  August 23 to September 15

Columbia:  September 15 to September 21

Yukon Avenue:  September 21 to 23

 

Work shift of the water and sewer crew is 10 days on, 4 days off.  Start at 6:00am.