 Kerrobert Street Project

Watermain Replacement Construction to Begin:

Please see the tentative schedule below: Please note that there may be changes in this schedule that are unforseen. This is only a tentative schedule. 

Mobilization of equipment and materials: To begin June 14

Atlantic Avenue: June 21 - July 14

Atlantic Avenue Downtown: Roads and sidewalks will begin July 6th, with the intent to complete by end of July. Existing sidewalks will remain in place as long as possible.

Manitoba Avenue: July 14 - July 26

Alberta Avenue: July 26 - August 23

Saskatchewan Avenue: August 23 - September 15

Columbia Avenue: September 15 - September 21

Yukon Avenue: September 21 - 23 

 

(Please click on links below to view important documents)

Proposed Local Improvement Plan for Street Reconstruction in Kerrobert

Sewer Main Replacement Map

 Roadway Upgrades Map

Roadway Phasing Map

Water Main Replacement Map

 Generalized Questions/Comments

Petition Validity Statement for Local Improvement

If you have any questions about the proposed local improvement plan and do not use email, please print off the form below, fill out and mail to:

Box 558, Kerrobert, SK S0L 1R0

(or drop off at the Town Office at 433 Manitoba Avenue) 

Local Improvement Question Form